When to book each stage inspection on a Clyde build

The order Clyde trades follow, and the window before each stage is covered.

Owner Inspections · Clyde 3978 · 2026-03-11

In short: Stage inspections are worth something only while the work is visible. This is the order Clyde builds run in and where the windows are.

The program decides your window

A Clyde volume build runs to a fixed program and trades follow each other closely. The gap between a stage finishing and the next trade covering it is often two or three days, which is the whole window you have.

Slab pre-pour

Book the day before the pour. Once concrete is placed, the steel, the pods and the vapour barrier are gone from view permanently.

Frame

The last look at structure. Bracing, tie-down and plumb can be measured now and not after sarking and plaster.

Lock-up

Cladding, roof and external doors are on. Sarking and door flashings are visible for a few days before the plasterer arrives.

Waterproofing

After the membrane and before the tiler. A membrane defect found here costs a morning; found later it costs the bathroom.

Pre-handover

About a week before practical completion, so you have the list before you are asked to sign.

Written by the Owner Inspections team from inspections carried out in Clyde. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.

Guides

More new construction stage inspections guides for Clyde

All guides →

Book a building inspection in Clyde

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Questions Clyde owners ask about this

Which two stages if I can only afford two?

Frame and pre-handover.

How much notice do you need?

A day or two, but tell us as soon as the date is set.

Do dates move?

Constantly. Keep us posted and we will follow the program.

Can I book all seven?

Yes, and it is the most complete record you can have of the build.